roll sublimation heat press manual..
roll sublimation heat press manual.
steps to you run with the rolling sublimation head transfer machine.
1 Open air switch , the main power button is pressed , the red indicator light , turn the heating switch , temperature controller green light , the unit starts heating .
2 temperature settings .
( 1 ) The bottom temperature controller DIP Digital dial at 250 ° C, a small green light to start automatic temperature control .
( 2 ) When the temperature is displayed about 250 ° C is reached, the red light indicates the temperature has to work to transfer .
( 3 ) If the transfer , the temperature is too low , set the temperature to increase more appropriate , whereas lowered more.
( 4 ) must be checked before each start over dial settings, to prevent people from setting too high and burn blankets.
( 5 ) Open the motor switch , which was appropriated forward on the governor from left to right slowly turn the knob to the proper speed can be.
3 How to transfer .
put the printed sublimation paper to the blanket , so it will be out all to the cloth or fabric ..
4 power handling .
In order to ensure the transfer finished , turn off the motor after the belt drive , this time can still transfer , the same effect ( note the speed to be consistent ) .
5 To ensure the transfer blanket life, please After each transfer , the dial is tuned to 95 ° C or less , the machine continues to rotate until the temperature drops below 100 ° C , you can stop.
two: analyze rolling sublimation head transfer machine different problems!
1 meter did not show after boot .
Solution: Check the power contacts are good
2 showing the motor , but it does not work.
Solution: check the power indicator light does not light :
( 1 ) may be exposed to bad .
( 2 ) the relay is good
3 high temperature table adjusting temperature , but the transfer is light in color ...
( 1 ) Check the relay switch .
( 2 ) heating the terminal ends of the tube in contact with power lines or bad connection in the heating roller is not good contact between the tube sheet .
( 3 ) may transfer temperature is not enough
( 4 ) blanket deviate .
( 5 ) according to the instructions carefully adjusted , to observe
( 6 ) heating time is very long, but still negative light in color
Solution: heating pipe is bad or aging
Solution: Check the voltage reaches 220V
( 7 ) Check the motor reversing relay can not be adjusted or the base is bad or if the motor is not damaged motor speed control switch is bad check volatility.